|
Hits: 22193
| Site updated on : 17.06.2013 |
हिन्दी
|
|
 |
NEYVELI LIGNITE CORPORATION LIMITED
नेयवेली लिग्नाइट कार्पोरेशन लिमिटेड
('Navratna' - A Government of India Enterprise)
Neyveli-607801, Tamilnadu, India.
|
Registered Office
No.135, Periyar E.V.R. High Road, Kilpauk,
Chennai - 600 010. Tamil Nadu,India.
Ph No.91-44-28364613 - 616, Fax. 91-44-28364625
|
|
|
|
| 1. TPS-II EXPANSION (2 x 250 MW) |
|
PROJECT INFORMATION:
1.
Station Capacity : 2 x 250 MW.
2.
GOI Approval : 18.10.2004
3.
Original sanctioned Cost : Rs. 2030.78 Crs.
COMMISSIONING
SCHEDULE: Anticipated
a)
COD of Unit-I: November 2012
b)
COD of Unit-II: March 2013
|
Package
Code
|
Package
Name
|
Contractor
Name
M/s.
|
|
|
Consultancy
Services
|
TATA
Consulting Engineers
|
|
A01
|
Main
Plant Package (BTG)
|
BHEL,
New Delhi
|
|
A02
|
Lignite
Handling system
|
MECON,
Ranchi
|
|
A03 (Phase I)
|
Ash
Handling system
|
Mc
Nally Bharat Engineering Co. Ltd., Kolkatta
|
|
A03 (Phase II)
|
Lean
Slurry System
|
Energo
Engineering Projects Limited, New Delhi
|
|
A04
|
Circulating
Water and Fire Protection system
|
Subash
Project Marketing Limited, Kolkatta
|
|
A05
|
Water
Treatment Plant
|
Driplex
Water Engineering Ltd., New Delhi
|
|
A06
|
Chimney
& Cooling Towers
|
Gammon
India Ltd., Mumbai
|
|
A08
|
400
KV Switch yards and Power Transformers
|
BHEL/TBG,
Bhopal
|
SALIENT FEATURES OF THE PLANT
This
is the first time that 250 MW Circulating Fluidized Bed Combustion
(CFBC) boilers are being installed in India, Neyveli.
The
Boiler is Designed, Supplied and Erected by BHEL, who are having a
technical tie up with M/s. LENTJES , GERMANY.
The
boiler is environment friendly in controlling oxides of Sulphur &
Nitrogen emissions. (SOX , NOX )
Slagging
/Clinker formation will also be much less in CFBC boilers.
Modern
ash collection system envisages 100% utilisation of fly ash for
cement and other industries.
TPS
II Expansion has fully automatic Lignite Handling System.
Fully
automated main plant is controlled by micro processor based DDCMIS,
with advanced technology.
Advanced
technology in water treatment in controlling regenerant chemicals
using RO/DM membrane process.
No
bore well water is used in this plant. Only storm water from mines
is treated and used for all water requirement of this plant.
The
beneficiaries from this power station are Tamil Nadu, Kerala,
Karnataka and Pondicherry states.
|
|
| 2. NLC TAMILNADU POWER LIMITED (2 x 500 MW) |
NLC
Tamilnadu Power limited (NTPL), is a subsidiary of Neyveli Lignite
Corporation Ltd (NLC) and a joint venture between NLC and M/s
TANGEDCO (Tamilnadu Generation and Distribution Company),
incorporated under the company act.
The
equity participation between NLC and TANGEDCO is at the ratio of
89:11.
GOI
had issued sanction for the implementation of coal based 2x500MW
Thermal Power Project by NTPL at Tuticorin at an estimated cost of
Rs.4909.54 Cr.
The
project is located in the Harbour Estate area of M/s V.O.
Chidambaranar Port Trust (VOCPT) and adjacent to the Thoothukudi
Thermal Power Station of TANGEDCO.
Land
for the project and residential colony has been allotted by VOCPT on
long term lease basis.
Service
water requirement for the plant and the potable water requirement
for the plant as well as township will be met from the Desalination
plant being set up at the project site.
All
the major packages for the project have been awarded. The main plant
package namely Steam Generators & Turbo Generators has been
awarded to M/s BHEL. Construction activities are progressing in
full swing and the commissioning of the first unit is expected by
December 2013 followed by the second unit in March 2014.
Power
Purchase Agreement has been signed with TANGEDCO,
ESCOMs of Karnataka State, Puducherry Electricity Department, Kerala
State Electricity Board, DISCOMs
of Andhra Pradesh.
Power
evacuation from this project is being carried out by M/s Power Grid
Corporation of India.
For
the long term coal linkage for the project, M/s Mahanadi Coalfields
Limited, a subsidiary of M/s Coal India Limited, issued Letter of
Assurance for the supply of “F” grade coal. Coal
is to be transported from Orissa by Rail-cum-Sea route through
Paradip Port.
Boilers
are designed to fire imported coal up to 30%.
A
dedicated coal jetty namely North Cargo Berth-1 (NCB-1) constructed
at VOCPT port will facilitate unloading of coal from ship. From
NCB-1, the Coal will be transferred through belt conveyors to the
Plant.
For
the residential accommodation of its employees, a township is being
set up.
|
| 3. NEYVELI NEW THERMAL POWER PROJECT (2 x 500 MW) |
|
Neyveli
Lignite Corporation Limited is developing a green field 1000 MW
Lignite fired Thermal Power Station as replacement for the existing
600MW Thermal Power Station-1 which has served for about 50 years.
The new power project called “Neyveli
New Thermal Power Project - (NNTPP)” is
located at Neyveli and will receive the primary fuel lignite from the
pithead mines of NLC Ltd. The power generated in this Station will be
shared among the southern states of Tamilnadu, Karnataka, Andhra
Pradesh, Kerala and Puduchery as per the directives of the Ministry
of Power. The proposed 2X500MW Power Plant when established, will
become the first lignite-fired 500MW Power plant in the country.
The
Govt. of India sanction for the project was received on
09.06.2011.The sanctioned cost of the Project is Rs 5907.11 crores
(October -2010 base). The tendering process for the project is
underway and the plant is expected to be commissioned within the 12th
plan period.
|
| 1. UTTAR PRADESH POWER PROJECT (3 x 660 MW - COAL BASED) |
It
is proposed to establish 4000 MW capacity coal based power project
in the State of Uttar Pradesh in 2 stages each having 2000 MW
capacity. The estimated cost of the project is around Rs.
14858.62
Crores.
MOU
was signed with M/s Uttar Pradesh Rajya Vidyut Nigam Limited
(UPRVUNL) for implementing the first phase of the project as a Joint
Venture with equity participation in the ratio of 51% (NLC) : 49%
(UPRVUNL).
Firming
of Project inputs like water allocation is completed and land
acquisition is in process. Coal linkage is yet to be obtained.
Power
Purchase Agreement has been signed with M/s Uttar Pradesh Power
Corporation Limited, within the time limit stipulated by Ministry of
Power,
Joint
Venture Agreement entered with UPRVUNL on 06.10.2012.
|
| 2. SIRKAZHI THERMAL POWER PROJECT (3 x 660 - MW COAL BASED) |
Sirkazhi
Thermal Power Project (STPP) is proposed with imported coal and it
is proposed to take up 2000 MW initially and increase it by another
2000 MW in the second and final phase at a cost of Rs.10395.00
Crores.
Site
selected in Thirumullaivasal village of Sirkazhi Taluk was inspected
by Site Selection Committee of Central Electricity Authority.
Power
Purchase Agreement was signed with Southern Electricity Boards
within the time limit stipulated by Ministry of Power.
Project
inputs like Land and coal linkage are to be firmed up.
|
| 3. BITHNOK THERMAL POWER STATION IN RAJASTHAN (1 x 250 MW - LIGNITE BASED) |
Project
Cost Rs.1670.54 Crs.
Power
Purchase Agreement was signed within the time stipulated by Ministry
of Power, with Distribution Companies (DISCOMS) of Rajasthan for
supplying entire power.,
Environmental
Clearance for the power project was received from State Pollution
Control Board and NOC from Aviation and Defense Department were
obtained.
50
Cusecs of water from IGNP canal has been reserved for Bithnok and
Riri Projects and water supply agreement is to be signed with IGNB.
Application
was submitted for Land Acquisition and Notifications were issued to
acquire the private lands. The High Power Committee constituted by
Government of Rajasthan in its meeting held on 06.07.2012 has
recommended the amount of compensation. The recommended
Compensation is under scrutiny by GoR. On approval by GoR, the
award is likely to be passed shortly which will complete the process
of acquisition of private lands.
M/s
Mecon has been engaged as Project Consultant and Tender documents
are under preparation.
Bithnok Mine:
Project
Cost Rs.349.77 Crs.
Application
was submitted to state forest department for diversion of Forest
land and it is under process.
Application
for issue of Mining Lease is under process by the State Mining
Department and will be issued after NOC for Forest Diversion is
obtained.
Environmental
Appraisal Committee has considered the project but sought
clarification on the mine closure plan. The Committee wanted NLC to
carry out a Social Cost Benefit Analysis to see whether the costs of
destruction of the socio-economic factors and livelihood is more
than the returns or profits on the investment made. These two issues
are holding up the environmental clearance.
Both
mine and power project proposal will be submitted to the NLC Board
after the linked Mining Project is cleared by Ministry of
Environment & Forest.
NLC
being Navratna Company, the Board has powers to approve the Mine and
Power Projects.
|
| 4. BARSINGSAR TPS EXTENSION (1 x 250 MW - LIGNITE BASED) |
Project
Cost Rs.1691.65 Crs.
Feasibility
Report was prepared by M/s Desein, New Delhi.
Water
allocation from IGNP is already available.
The
power station is to be located within the premises of the existing
Barsingsar Thermal Power Station and hence no fresh land is required
for TPS.
Power
Purchase Agreement was signed within the time stipulated by Ministry
of Power, with Distribution Companies (DISCOMS) of Rajasthan for
entire power.
Environmental
Clearance obtained for the project.
NOC
from Aviation and Defense Department were obtained.
Linked mining projects are Hadla & Palana.
Project Cost Rs.350.13 Crs.
Hadla Mine:
In
respect of Hadla Mine, Feasibility Report was prepared by M/S CMPDI
and EIA / EMP Report was prepared by M/s Kirloskar Consultants,
Pune.
Public
Hearing was conducted and the proposal was discussed by
Environmental Appraisal Committee for issuing Environmental
Clearance (EC). Committee has recommended for issue of EC.
Application
was submitted to Government of Rajasthan for land acquisition and is
under process. Land acquisition notice was issued in July 2012.
Mine
Plan approval was obtained and application was submitted for issue
of Mining Lease, which is under process.
Palana Mine:
Feasibility
Report has been received from M/s CMPDI and EIA / EMP Report is
under preparation by M/s Kirloskar Consultants, Pune.
Application
has been submitted to MOE&F for fixation of Terms of Reference
(TOR) for preparation of EIA / EMP Report. MOE&F held the TOR
meeting for the project on 27.08.2012.
Proposal
for Transfer of Mining Lease in favour of NLC was forwarded by the
Government of Rajasthan to Ministry of Coal.
NLC
has deposited the amount with M/s Rajasthan Vidyut Pracharan Nigam
Limited (RVPNL) towards 7334 Bighas of land, which is to be surveyed
and transferred to NLC.
|
| 5. JOINT VENTURE COAL MINING PROJECT IN ODISHA (20 MTPA) |
Project
Cost Rs.447.72 Crs.
A
Joint Venture Company viz., M/s MNH Sakthi Limited was formed by M/s
MCL, NLC & M/s HINDALCO as per the direction of Ministry of
Coal, with equity participation in the ratio of 70% : 15% : 15%, to
develop and mine Talabira 2 and 3 coal blocks in Talcher Coal Fields
of Odisha and share the production in the same ratio.
M/s
Mahanadi Coalfields Limited M/s MCL) being the major partner,
carrying out all the project activities for developing the Mine.
|
| 6. WIND POWER PROJECT |
Based on the
approval given by the Board, NIT issued on 20.04.2012 to fix up
agency for setting up 50 MW Wind Power Project at one or two
locations anywhere in India at an estimated cost of Rs.364.75 Crores
which includes O&M services for the first five years. Tender
opened on 12.09.2012. Three bids received and bid evaluation is in
progress.
|
| 7. SOLAR POWER PROJECT |
It is proposed to
install 10 MW crystalline based Photo Voltaic Solar Power Project at
Neyveli (near the airstrip) in the first phase which will be
increased to 25 MW in the second phase. For fixing up of agency for
installing 10 MW Solar Power Plant at an estimated cost of Rs. 133
crores, tender was floated on 13.03.2012. Tender was opened on
04.05.2012. 13 bids were received and 10 bids were Short-listed.
Techno-Commercial evaluation is in progress.
|
|